Saturday, May 19, 2007

the market has begun

Today was the first of many farmer's markets. Paul and I started baking at 1am this morning, and actually got to the market with lots of time to spare. After baking for most of the night, the market is a very satisfying way to end the work day. So many people so eager to take home a bit (or a lot) of what we worked so hard on. Not that it all makes it all the way home. Even the sun came out for our first market. Back to cleaning up posts tomorrow. I wonder what the neighbours would say if I got up at 1am and fired up the chainsaw?

Thursday, May 17, 2007

check out our beams

They are long, smooth, and have gorgeous grain.

We spent today sanding beams, moving beams, and sanding beams. Our posts are all milled now, so the crew can start prepping them for installation as well.

Not much else to report. We're planning to mix and pour the slab on Tuesday. Stay tuned.

First Farmer's Market of the season this Saturday. I'm not sure that I feel like getting up at 1am to start baking, but there are only about 22 markets, so we better make the best of them.

Wednesday, May 16, 2007

sawdust, sawdust, everywhere

We might not be able to work on the oven right now, but the building site was a busy place today (even if its not obvious from the photo). Our logs were being milled into lumber, posts, and beams. Our beams were being sanded and prepped for installation once the posts and purlins are in place. Okay, when I summarize that way, it doesn't sound like that busy of a day, but it was, with lots of people working.

All in all, it was another lovely day on Gabriola. The only problem is that it is way past beer time.

Tuesday, May 15, 2007

ready for cement slab (almost)

The oven is ready for the slab to be poured, but we aren't. We need more "needles". For each bag of cement we use for the slab, we need to add 1 pound of 1" long stainless steel needles to give it added strength to span the 3 foot gaps on each side of the oven. Hopefully the back ordered needles will arrive soon.

The top photo is the completed layer of insulating bricks. The middle picture is of the completed plywood forms supported underneath by short 2x4 posts (check the Picasa web album to see these). There is a ring of 1x4" strips around the top to hold the 4 inch thick slab.

The bottom picture is of one of our many 6x10 beams being sanded. The fir is beautiful after a bit of sanding. We only have about 38 more hours of sanding to go!

Monday, May 14, 2007

back to work

After a slow Saturday and slower Sunday, I went into Nanaimo today to pick up our much needed zonolite. When I got back, our contractor's crew were busy preparing for the next building stage. They had peeled the bark off most of the logs, and were setting up an Alaskan chainsaw mill to start getting the posts ready.

Paul and I topped up the zonolite, then added a bunch more insulating bricks to the left side of the oven. We got most of the center support wall covered with insulating bricks as well. There are still some bricks to lay, but we should be ready to start building forms for the slab tomorrow.

Saturday, May 12, 2007

slow day

We picked up all the perlite we could find on Gabriola this morning, but still came up a bit short. We placed a few more insulating bricks on the right side, but couldn't go much further. The slab will sit on a full ring of bricks as set up on the right side of the oven. The wall down the middle will also be covered with insulating bricks, and those will support the slab down the middle.

We peeled a few more logs that will be suitable for posts, but then kind of ran out of bakery things to do. I guess it is the weekend, but it feels strange with nothing to do. I might have to get some work done around the house!

Friday, May 11, 2007

brick laying

Today we mixed our zonolite with cement and water and shoveled it on top of the wonder board. We leveled it and started placing insulating bricks. We finished the bottom layer of bricks on the right side of the oven. There are more layers of bricks to go on, and we need some more zonolite for the left side. The opening you see in the photo is for the chimney ducting. The heated air will flow from the top of the fire box around the semicircle, and out the ducting. The slab and hearth bricks will sit above the insulating bricks to come. They will be supported around the edges and down the middle. More details on the slab when we get to it.

We have lots of sun in the forecast, so it is great to be able to work outside and listen to music and the birds and frogs. Its a wonderful feeling watching our oven grow everyday. Soon the bakery will start growing again as well.

Thursday, May 10, 2007

photo albums

If you would like to browse through the photos of either the building of the bakery, or just of the wood oven, feel free to go to my picasa web album. I will try to add a few more photos of the oven construction to the album as time allows.

progress

Today we continued with the oven. We started building the fire box, using both insulating bricks (white), and fire bricks (orange). The fires will be built on a grate which sits on the supporting rows of bricks along the edges of the bottom of the the fire box.

We also cut and installed most of the wonder board in the base of the oven, which will get covered with a mixture of zonolite and portland cement tomorrow. The zonolite mix will be around 10" thick. On top of that will be many more insulating bricks.

We also received more logs to peel today, and maybe we'll get around to some more peeling and milling tomorrow.